Risk

This is a P6 field supported by the Integration app.

Description: The risk object represents a probabilistic event or condition which if it occurs has an impact on the project.

P6 Field

Description

Read-Only

Cause

The description of the cause of the Risk.

No

Description

The description of the Risk.

No

Effect

The description of the risks effect on the project.

No

Id

The ID of the Risk. Must be unique within a project.

No

IdentifiedDate

The date this risk was identified.

No

Name

The name of the Risk. Does not need to be unique.

No

ObjectId

The unique ID generated by the system.

No

ProjectId

The short name of the associated project.

Yes

ProjectObjectId

The unique ID of the associated project.

No

ResponseTotalCost

The total estimated cost for the risk.

No

Status

The current status of the Risk. Valid values are 'Proposed', 'Open', 'Rejected', 'Managed', and 'Impacted'.

No

Type

The type of the risk. Valid values are 'Threat' and 'Opportunity'.

No