Set the Progress Measure for a Work Package
Setting the Progress Measure option enables you to determine how progress is measured against scope assignments in work packages.
To set the progress measure:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Work Packages.
- In the table, select the work package.
- Select the General detail window.
- Select the Progress Measure option.
- Milestone Percent Complete: This option uses a selected Rule of Credit to measure progress.
- Physical Percent Complete: This option allows users to manually enter Installed Quantity for scope assignments.
- If Milestone Percent Complete is selected, select options for the following:
- Rule of Credit Method: A defined set of milestones that are used to show progress for each scope assignment in the work package.
- Progress Type: Select Sequential if milestones must be completed in order, or select Non Sequential if order does not matter for the rule of credit.
- Select Save.