Change the Status of a Project
The current status of a project determines how the project is handled within the application. Project status can be set manually or through a workflow, depending on the status type. A new project is set to Active by default.
To change the status of a project:
- Navigate to the project Details page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Details.
- In the Details section, in the Status list, select the appropriate status:
- Proposal: The project is a project proposal and has not been extensively planned nor accrued any costs. A project proposal can only be created using a workflow and a change in status must also be performed through a workflow.
- Rejected: The project proposal has been rejected and will not be executed as a project. A project can only be marked as Rejected through the use of a workflow.
- Planned: The project is currently planned for execution. Project managers input expected project costs and other project data during this stage. A change in status can be performed manually or through a workflow.
- Active: The project is currently active and being executed. A change in status can be performed manually or through a workflow.
- Inactive: The project has been rendered inactive and will temporarily accrue no costs. A change in status can be performed manually or through a workflow.
- Complete: The project has been successfully completed and will no longer accrue costs. A change in status can be performed manually or through a workflow.
- Select Save.