Configure Schedule Settings for a Project
Configure project schedule settings to set planned project start and finish dates, as well as a date by which the project must finish. These dates are also used to drive the project scheduler during the scheduling process.
To configure schedule settings for your project:
- Navigate to the project Details page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Details.
- In the Schedule section, in the Project Planned Start field, select the start date.
- In the Project Planned Finish field, select a planned finish date.
- In the Schedule Must Finish By Date field, select the date the project must finish by.
- Select Save.
This setting is used in the following apps:
Resources |
Risk |
Schedule |
Scope |
Tasks |