Assign a Manager to a Project
Assign managers to projects to identify the project manager or person responsible for managing the project.
The user who created the project is automatically assigned as the manager.
To assign a manager to a project:
- Navigate to the project Details page
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Details.
- In the Details section, in the Manager field, select a manager.
- Select Save.
You can also do this on the Projects page.
- In the object selector, select ﱆ Project, and then select View Projects List.
- In the table, select a project, and then add a manger in the Manager field.
This setting is used in the following apps:
Cost and Funds |
Resources |
Risk |
Schedule |
Scope |
Strategic Alignment |
Tasks |