Add a New Work Package to a Change Request
Add work package change item requests when new work packages are needed for a project. A work package change item request is added to a work package change request, where one or more change items can be added.
To request a new work package:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Work Package Changes.
- In the table, select the ID for the work package change request.
- On the Work Package Changes details page, select the Add Work Packages tab.
- Select Add.
- In the Add Work Packages dialog box, complete the following fields:
- Name: Enter the name of the work package.
- ID: The ID is generated automatically based on project settings. Adjust as needed.
- WBS: Select the WBS to associate with this work package.
- Start: Select the date the work on the work package is scheduled to begin
- Finish: Select the date the work on the work package is scheduled to finish.
- (Optional) Manager: Select a project manager or person responsible for managing the work package.
- (Optional) Description: Enter description for the work package.
- Select Save.
Notes:
- If you want to add scope assignments to the work package, you must add scope assignments to the same change request.
- To edit details of the work package request, select the Work Package ID.
Last Published Tuesday, November 19, 2024