Approve or Reject a Potential Change Order Proposal
After subcontractors have submitted proposals related to a potential change order, you must approve the proposals to proceed to the next step of the change process. Alternatively, you may reject a proposal and work with the subcontractor who submitted it to adjust its values as needed.
To approve or reject a potential change order proposal:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Contracts and Commitments, and then select Potential Change Orders.
- On the Potential Change Orders page, select a potential change order.
- On the Proposals tab, find the proposal that you want to approve or reject.
- Select the Context menu, and then select Approve Proposal or Reject Proposal.
- In the Approve Proposal dialog box, in the Notify Users field, select any users who you want to be notified of the change.
- In the Comment field, enter any additional information about your decision.
- Select Approve or Reject.