View Risk Iteration Analysis Results
View the first fifty iterations that were calculated during risk analysis to see the potential outcomes of your schedule and cost based on the Monte Carlo analysis. Compare activity deterministic values with the random schedule and cost impacts in each iteration.
To view risk iteration analysis results:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Risk, and then select Risk Iteration Analysis.
- On the Risk Iteration Analysis page, in the dropdown list in the toolbar, select to view the Pre-Response or Post-Response analysis.
Note: When a risk analysis is run for either pre-response or post-response, all existing pre-response and post response data is cleared in order to show the most up to date, non-conflicting data. To compare pre-response and post-response data, run risk analysis for both scenarios.
- On the Layout menu, select Grid to view only the grid or select Gantt to view both the grid and Gantt chart.
- Navigate through the iterations by selecting the Next iteration, Previous iteration, Jump to last iteration, and Jump to first iteration arrows. Enter a number in the Iteration field to view a specific iteration.
Two bars are shown on the Gantt chart for each activity: one is the deterministic value (the activity dates based on the current schedule), and the second is the iteration value (the projected dates randomly generated based on activity uncertainty and potential risks). Hover over a bar on the Gantt chart to view the detailed impacts on the activity for the iteration. Select the Weather Non-Working Days toggle to view the non-working days due to weather on the Gantt chart.
Tips
- To add a column to the table, select the Open Column Selector icon, and in the column dropdown, next to a column name, select Show or Hide to add or remove the column.
- When activity date indicators are enabled, the risk analysis displays indicators for the Start and Finish dates of activities that have actual dates or assigned constraints. When the As Late As Possible constraint is selected, the constraint indicator is not displayed. See Configure Activity Date Indicators to enable indicators.
- Select an activity to view the Risk Impacts, Relationships, and Resource Assignments in the detail window.
- Below the Gantt chart, select Gantt Settings to configure Gantt chart settings such as the timescale, currency options, and more.
Last Published Tuesday, November 19, 2024