Risk Management Integration with P6 EPPM
Integration between Oracle Primavera Cloud and P6 EPPM enables you to import data from a P6 EPPM project into Primavera Cloud where you can use the application to perform qualitative and quantitative risk analysis. This can be beneficial in circumstances where you manage your project schedule in P6 EPPM, but you want to take advantage of the advanced risk management capabilities of Primavera Cloud.
Using P6 EPPM to import Schedule data only (for Schedule)
When you import project schedule data into Primavera Cloud, data that is sent from P6 EPPM to the application includes all your schedule data. After this data is imported into Oracle Primavera Cloud, you can run a quantitative risk analysis. The system uses the activity data as inputs for the analysis process to determine how the identified risks can impact the durations and dates of your project activities.
Using P6 EPPM to import both Schedule and Risk data (for Risk)
When you import project risk data and project schedule data into Primavera Cloud, data that is sent from P6 EPPM to the application includes all of your schedule data plus risk thresholds, risk matrixes, and data from the project risk register. After this data is imported into Primavera Cloud, you can perform a qualitative analysis to assess and prioritize the risks identified for your project. You can also run a more detailed quantitative analysis. The system uses the activity data as inputs for the analysis process to determine how the identified risks can impact the durations and dates of your project activities.
Update P6 EPPM with Risk Analysis results from Oracle Primavera Cloud
When the analysis is complete, key schedule dates returned from the analysis can be exported back to P6 EPPM to update the project in that application. Risk analysis results that can be exported back to a P6 EPPM project include:
- Pre-response and post-response pessimistic start and pessimistic finish dates for each project activity.