Update the Data Date When Progressing a Work Package and Scope Assignment
When adjusting work package or scope assignment dates, update the data date to adjust all key date fields. This will adjust the Original, Planned, Revised, and Remaining dates.
Note: This only applies when activities are not linked to work packages or scope assignments.
To update the data date:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Work Packages.
- Select Modify Dates.
- In the Modify Dates dialog box, select a new data date and select Modify.
Tips
- When activities are linked to work packages or scope assignments, dates are updated when the scheduler is run.