Review the Time Phase Distribution for a Scope Assignment
View the time phased distributed data for work package scope assignments to analyze quantity, hours, and cost.
Configure the Time Phase view to enable you to view information that is important when monitoring the progress of work on scope assignments.
To configure the time phase data:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Scope Assignments.
- On the Scope Assignments page, in the Work Package field, select the name of the work package.
- Select Time Phase.
- Configure the quantity, hours, and cost spreadsheet rows to review in the table. For more information, see link
- Configure the timescale to view quantity, hours, and cost. For more information, see timescale link.
If you chose a Reporting Period, select whether to only display the custom label that is configured for the reporting period.
- To view a specific date, in the Go to field, select a date. This will also synchronize dates in the table and chart.
- To configure the chart view:
- In the Show list, select whether to view data by Quantity, Hours, or Costs.
- In the View list, select whether to view Incremental or Cumulative values.