Complete an Activity or Milestone
You can mark your milestones and in-progress activities as complete.
Note: After you mark an activity or milestone as complete and then save it, you cannot revert its status to in-progress on the My Activities page. This can only be done on the Activities page, usually by a manager.
To mark a milestone or activity as complete:
- In the header, select your username, and then select My Activities.
- Select List to enter the List view.
- In the activity list, select the activity or milestone that you want to complete.
- Select Mark Activity Complete.
- Select Save.
Tips
- You can also mark an activity as complete in the Grid view. Select the Context menu for the row that represents an activity that you want to complete, and then select Complete Activity.