Link a Work Package to an Activity
Link work packages to activities when you want to manage work package dates using activity dates.
Note: Schedule costs and scope costs are calculated separately. Linking a work package or scope assignment with an activity won't link the costs.
To link an activity to a work package:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- In the table, select the activity.
- On the Layout menu, select Activity Details, and then select the General detail window.
- In the Work Package Name field, select a work package.
Note: You can only link an activity to a work package that belong to the same WBS that is associated with the activity.
- All changes made to this page are saved automatically.