Copy a Parent Workspace CBS
Copy the parent workspace CBS if your project will use the same CBS as the workspace. You can keep your project up-to-date with the workspace CBS by importing additional CBS codes at any time.
To copy a parent workspace CBS:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Cost and Funds, and then select Cost Sheet.
- On the Cost Sheet page, select Create CBS.
- In the CBS Setup dialog box, select Copy from other, and select Next .
- Select the CBS you want to copy, and then select Next .
- Select the CBS hierarchies you want to include, and then select Next .
- Select one or more budget or actuals sources, and select Finish.