Assign a Scope Item to a Work Package
Select the materials or products needed to complete work packages.
Note: After a baseline is set, scope items must be assigned to work packages by submitting a change request.
To assign a scope item to a work package:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Scope, and then select Scope Assignments.
- On the Scope Assignments page, in the Work Package field, select the name of the work package.
- Select Plan.
- Select Add.
- On the Select Scope Item panel, select all the scope items needed for the work package and select Select.
- In the General detail window, complete the following fields for each assigned scope assignment:
- Original Quantity: The amount needed for this work package. The Unassigned Quantity is prepopulated in this field.
- Original Productivity Rate: This field is prepopulated with the rate initially defined for the scope item. Update as necessary. Updates are only reflected in this scope assignment.
- Original Hours: This field is calculated by multiplying the Original Quantity times the Original Productivity Rate. If you change this value, the Original Productivity Rate is recalculated.
- Rate By: Determines whether the cost is calculated using Quantity or Hours. If the cost of assignments is not relevant for your calculations, then leave the Original Cost Rate field as 0.
- Quantity: Quantity is used to calculate cost. For example, Original Cost is calculated as Original Quantity times Original Cost Rate.
- Hours: Hours are used to calculate cost. For example, Original Cost is calculated as Original Hours times Original Cost Rate.
- Original Cost Rate: The rate used to calculate cost. Depending on the Rate By selection, this rate is either based on the rate per quantity or hours.
- Select Save.