Add a Rule of Credit
Add rules of credit for tracking progress on scope assignments when the work package progress measure is set to Milestone Percent Complete.
To add a rule of credit:
- In the object selector, select Workspace, select View Workspaces List, and then select a workspace name.
- From the Main Menu, select Summary & Settings.
- On the Summary & Settings page, select Dictionaries, and then select Rules of Credit.
- Select Add.
- In the Name field, enter the name for the rule of credit.
- In the Input Type list, choose how to apply the rule of credit:
- Manual: Enables users to enter their percentage complete on a milestone. Use this option if it is important to track the percentage complete on a milestone.
- 0/100 Percent Complete: Enables users to mark a milestone as complete. Use this option if it is important to show whether the work is complete or not complete. A weighted percentage is still applied to enable a percentage complete rollup at the work package level.
- Use the table to define milestones used to track percentage complete.
- In the Milestone Name field, enter the name of a milestone.
- In the Incremental Percent Complete field, enter the percentage each milestone represents for the rule of credit. The Cumulative Percent Complete must equal 100%.
- Select Save.
Tips
- A rule of credit cannot be deleted if it is applied to a work package.
This setting is used in the following apps:
Scope |
Last Published Tuesday, November 19, 2024