WBS Fields
Depending on your settings, the following fields might appear on the page as table columns, spreadsheet rows, or in detail windows. Fields that are generic across the application, such as Name, may not be included here.
General
Added By
The username of the user that added the item.
Completed Activities
Total number of Completed activities for the WBS element in the current schedule. The number includes all activities which are part of any child WBS.
Current BL Completed Activities
Total number of activities associated with the WBS in the current baseline. The number includes all activities which are part of any child WBS.
Current BL In Progress Activities
Total number of in progress activities associated with the current baseline. The number includes all activities which are part of any child WBS.
Current BL Not Started Activities
Total number of not started activities associated with the WBS in the current baseline. The number includes all activities which are part of any child WBS.
Current BL Total Activities
The total number of activities associated with the WBS in the current baseline. The number includes all activities which are part of any child WBS.
Date Added
The date the activity was added.
Date Last Modified
The date when the activity was last modified.
Description
A brief description of the activity.
In Progress Activities
The total number of in progress activities associated with the WBS in the current schedule. The number includes all activities which are part of any child WBS.
Last Modified By
The last user who modified the activity.
Manager
The user name of the user set as the manager or contact for the WBS. The user who created the WBS is set as the owner by default.
Not Started Activities
The total number of not started activities associated with the WBS in the current schedule. The number includes all activities which are part of any child WBS.
Original BL Completed Activities
The total number of completed activities under the WBS in the original baseline. The number includes all activities which are part of any child WBS.
Original BL In Progress Activities
The total number of in progress activities under the WBS in the original baseline. The number includes all activities which are part of any child WBS.
Original BL Not Started Activities
The total number of not started activities under the WBS in the original baseline. The number includes all activities which are part of any child WBS.
Original BL Total Activities
The total number of activities under the WBS in the original baseline. The number includes all activities which are part of any child WBS.
Supplementary BL Completed Activities
The total number of completed activities under the WBS in the supplementary baseline. The number includes all activities which are part of any child WBS.
Supplementary BL In Progress Activities
The total number of in progress activities under the WBS in the supplementary baseline. The number includes all activities which are part of any child WBS.
Supplementary BL Not Started Activities
The total number of not started activities under the WBS in the supplementary baseline. The number includes all activities which are part of any child WBS.
Supplementary BL Total Activities
The total number of activities under the WBS in the supplementary baseline. The number includes all activities which are part of any child WBS.
Total Activities
The total number of activities under the WBS in the current schedule. The total number includes all activities which are part of any child WBS.