RiskResponseAction
This is a Primavera Cloud field supported by the Integration app.
Description: The risk response action object contains the detailed steps that need to occur to complete the risk response plan. Multiple actions can be associated with one response plan and each action can be linked to an activity in the project.
Primavera Cloud Field | Description | Read-Only |
---|---|---|
activityCode | The activity assigned to a risk response action item. | Yes |
activityId | The unique ID of the associated activity. | No |
finishDate | The latest finish date of all response action items. | No |
plannedFinishDate | The latest scheduled finish date of all the response action items. | No |
plannedStartDate | The earliest scheduled start date of all response plan action items. | No |
projectCode | The short name of the associated project. | Yes |
projectId | The unique ID of the associated project. | No |
projectRiskCode | The short name of the associated risk. | Yes |
riskMitigationCode | The unique identifier for the risk response plan action item. | No |
riskMitigationId | The unique ID generated by the system. | No |
riskMitigationName | The name of the risk response plan. | No |
riskMitigationStatus | The status of the response action item. The valid values are: Proposed, Sanctioned, Rejected, In-Progress, and Complete. | No |
riskResponsePlanCode | The short name of the associated risk response plan. | Yes |
score | The risk score from the numeric PID after the response action has been completed. | Yes |
startDate | The earliest start date of all response plan action items. | No |
Last Published Wednesday, October 16, 2024