Consume a Fund
After a fund has been added or allocated to a program, you can specify how much money in the fund has been consumed. Consumed money is money that has been spent to complete work in a program.
To mark a portion of a program as consumed:
- In the object selector, select Program, select View Programs List, and then select a program name.
- From the Main Menu, select Cost and Funds, and then select Program Funds.
- In the Status view, select a fund row.
Alternatively, if you are working with a time-phased fund, select the Time Phase view and then select a fund row.
- In the Consumed field, enter the portion of the fund that has been used.
For time-phased funds, each time period has a Consumed field, which you can use to specify how much money has been consumed for that time period.
- Select Save.
Tips
- To add and remove columns on this view, select Settings.
Last Published Tuesday, November 19, 2024