Workspace Summary Cost Sheet Fields
Project Cost Sheet
Financial
Project CPI
The measure of a project's cost efficiency.
A value of less than 1 indicates the project is over budget, while a value greater than 1 indicates the project is under budget.
Project Current Actuals
Total costs accrued on a project within a given time period.
The Actual Cost data for the project's life cycle is pulled from the P6 EPPM schedule.
Actual Cost data is only available when the application is connected with P6 EPPM and is not editable.
Project Current Budget
The total cost of the project budget, including all transfers and changes. This value is based on the base currency with specified exchange rate.
Project Current Commitments
The total cost of all approved commitments and approved change commitments on the project.
Project Current Contracts
The total cost for all current project contracts.
Project Earned Cost
The cost value used for the project's Earned Value Management, which allows project managers to quantify project progress and objectively measure the project's success.
Hours
Project Actual Hours
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
Project Earned Hours
Calculated as Performance Percent Complete multiplied by BAC Hours.
Project HPI
Calculated as the total of Project Earned Hours divided by Project Actual Hours.
Scope
Earned Value
Scope BAC Cost
The Revised Cost or At Completion Cost at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Cost of the current project if no baseline is set.
Scope BAC Hours
The Revised Hours or At Completion Hours at the time the current baseline was set, depending on the selection for the Budget At Completion Method. The Revised Hours of the current project if no baseline is set.
Scope EAC Cost
Calculated as ETC Cost plus Actual Cost to Date.
Scope EAC Hours
Calculated as ETC Hours plus Actual Hours to Date.
Scope Earned Cost
Calculated as Performance Percent Complete multiplied by BAC Cost.
Scope Earned Hours
Calculated as Performance Percent Complete multiplied by BAC Hours.
Scope ETC Cost
The estimate of the cost needed to complete the work.
Calculated as BAC Cost minus Earned Cost.
Scope ETC Hours
The estimated number of hours needed to complete the work.
Calculated as BAC Hours minus Earned Hours.
Financial
Scope Actual Cost to Date
The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done).
Scope Adjusted Cost
The amount the scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
Scope Approved Change Cost
The sum of all approved cost changes in the change records for the scope assignment.
Scope At Completion Cost
The total cost at the completion of the scope assignment.
Calculated as Revised Cost plus Adjusted Cost.
Scope Baseline Cost
The Revised Cost at the time the current baseline was set.
Scope Installed Cost
The total cost incurred on the scope assignment as of the current date.
If Rate By is set to Hours, then Installed Cost equals Revised Cost Rate multiplied by Installed Hours.
If Rate By is set to Quantity, then Installed Cost equals Revised Cost Rate multiplied by Installed Quantity.
Scope Original Cost
The original cost of the scope assignment.
If Rate By is set to Hours, then Original Cost equals Original Hours multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Hours.
If Rate By is set to Quantity, then Original Cost equals Original Quantity multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Quantity.
Scope Pending Change Cost
Calculated as the sum of all pending cost changes in the change records for the scope assignment.
Scope Remaining Cost
The amount left to be spent.
If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.
If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate.
Scope Revised Cost
The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost.
Hours
Scope Actual Hours To Date
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
Scope Adjusted Hours
The amount of scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
Scope Approved Change Hours
The sum of all approved change hours in the change and transfer records for the scope assignment.
Scope At Completion Hours
The total hours expected for the scope assignment.
Calculated as Revised Hours plus Adjusted Hours.
Scope Baseline Hours
The Revised Hours at the time the baseline was set.
Scope Installed Hours
Hours spent on the scope assignment.
Calculated as Installed Quantity multiplied by Revised Productivity Rate.
Scope Original Hours
The original expected hours needed to complete all the work required to install the material quantity on the scope assignment.
Calculated as Original Quantity multiplied by Original Productivity Rate.
Before the baseline is set, this field can be entered manually. A manual entry recalculates the Original Productivity Rate to equal Original Hours divided by Original Quantity.
Scope Pending Change Hours
Calculated as the sum of all pending hour changes in the change records for the scope assignment.
Scope Remaining Hours
The number of hours left for the scope assignment.
Calculated as Remaining Quantity multiplied by Revised Productivity Rate.
Scope Revised Hours
Original Hours before the baseline is set. After the baseline is set, Revised Hours is equal to Original Hours plus Approved Change Hours.
Last Published Tuesday, November 19, 2024