Configure Schedule Health Score Settings

Schedule Health Score metrics have default descriptions, target threshold values, and weight calculation values that can be modified in the project settings. You can also modify additional check criteria where applicable. Individual checks can be enabled or disabled according to your organization's needs.

To configure settings for the Schedule Health Score tool:

  1. Navigate to the project settings page
  2. Select the Schedule Health Check tab.
  3. Select Ignore Completed Activities if you want to exclude completed activities from the analysis.
  4. In the table, select a check, and then configure the following settings:
    • Description: Modify the description of the check depending on your organization's needs.
    • Active: Include the selected check in the Schedule Health Score panel. Only active checks are used in the schedule health score calculation.
    • Target: Set the target threshold percentage value for the check. Typically, a check that exceeds the threshold value is marked red in the Schedule Health Score panel.
    • Weighting: Set the numerical weighting of the check. This value is used when determining the overall schedule health score.
  5. In the General detail window, you can view or modify the same check details as in the table. Some checks have additional metrics that you can modify in the Criteria section of the detail window.
  6. Save your changes:
    1. Select Save.
    2. In the Summary & Settings panel, select Close.

This setting is used in the following apps:

Schedule