View the Schedule Health Score Results

Video

Use the results of the Schedule Health Score tool to identify activities that could negatively impact the outlook of your project schedule.

Each check provides the following information:

Typically, checks with higher percentage scores require more immediate attention. Individual check scores contribute to an overall schedule health score. A higher schedule health score indicates a higher quality schedule. Schedule checks are run against the current schedule or a schedule scenario.

Note: Some check scores are calculated after saving your data, while other scores are calculated after scheduling the project. Before using the Schedule Health Score tool, you should schedule the project to ensure you are viewing all the latest results.

To view the schedule health check results:

  1. Navigate to the project Activities page
  2. Select Schedule Health Score.
  3. In the panel, select a check to view the activities that do not meet the check metric's criteria. Select an activity to highlight it in the grid.
  4. Modify the activity details that relate to the check, and then schedule your project to view updated check scores.

Tips