Modify Activity Details in the Gantt Chart
You can modify a variety of activities and relationship details directly in the Activities page Gantt chart. Create activities, adjust durations and dates, and establish relationships between activities. Add lag to relationships, or modify the relationship type. Hover over an activity or relationship line to view its details.
To modify activity details in the Gantt chart:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- Select the Gantt icon.
- In the Gantt chart, you can make the following changes:
- To create an activity, right-click a row, and select Add Above or Add Below. Enter an activity name.
- To modify an activity's start or finish date and its duration, select the left edge or right edge of an activity bar and drag it to a new date. The new date and duration are shown next to the bar as you drag it.
- To modify an activity's start and finish dates without changing its duration, select the middle of the bar and drag it to a new date. The new start and finish dates are shown next to the bar as you drag it.
- To delete an activity, right-click an activity bar, and select Delete Activity.
- To create a relationship, hover over the left edge or right edge of an activity bar. Select the circle that appears and drag it to an edge of a different activity bar. A popover shows the proposed relationship and its type.
- To edit an existing relationship, select a relationship line, and then select Edit Relationship. In the popover, edit the relationship type and lag, and then select Apply.
- To delete an existing relationship, right-click a relationship line, and then select Delete Relationship.
- Drag any activity bar past the data date line to set a Start On or After constraint.
- All changes made to this page are saved automatically.
Tips
- You cannot add an activity while in a baseline.
- You can select multiple activity bars and edit their durations or dates at the same time.
- Milestone start or finish dates cannot be modified in the Gantt chart.
- When activity date indicators are enabled, the Gantt chart displays indicators for the Start and Finish dates of activities that have actual dates or if the activity has assigned constraints. See Configure Activity Date Indicators to enable indicators.
- For Level of Effort and WBS Summary type activities, weather risks are ignored and not included in the risk analysis. Cost impact is still included.
- The schedule impact of a risk mapped to Level of Effort and WBS Summary type activities is ignored and not included in the risk analysis. Cost impact is still included.