Void a Change
You can void a change that should no longer be documented as having any impact on your commitments.
To void a change:
- In the object selector, select ﱆ Project, select View Projects List, and then select a project name.
- From the Main Menu, select Contracts and Commitments, and then select Changes.
- On the Changes page, select the change that you want to void.
You can only void changes that are In Progress.
- Select the Actions menu, and then select Void.