Assign a Percent Complete Type to Activity
The percent complete type determines the way in which the application calculates the percent complete for an activity. Use the General detail window to assign percent complete types to activities.
To assign a percent complete type to an activity:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- In the table, select the activity.
- On the Layout menu, select Activity Details, and then select the General detail window.
- In the Percent Complete Type list, select an option:
- Physical: Percent complete is manually entered by a user based on the amount of physical work completed on the activity.
- Duration: Percent complete is calculated from the actual and remaining duration.
- Units: Percent complete is calculated from the actual and remaining units.
- Scope: The percent complete for the activity is derived from the scope percent complete of the linked scope assignments.
- All changes made to this page are saved automatically.