Reset the Project CBS

You can reset the project CBS if your project cost code needs change if the following conditions are met:

To reset the project CBS:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Cost and Funds, and then select Cost Sheet.
  3. On the Cost Sheet page, select the Actions menu, and then select Reset CBS.